The old adage of Time is Money rings out loud when I think of the
Cost of Project Commencement Delay.
In the past 3 months, I’ve worked with many
clients who have experienced delay with their project commencing. I will talk
about 3 of them to highlight where things went wrong and what a builder or
commercial contractor could do to manage this risk.
3 Projects
that suffered from a Delay with Project Commencement
Richie the
Cost Plus Builder – Up to $1M Contract
The builder was approached by a long term client
to refurbish another one of his residences. The client had obtained all the
compliance documents for the refurbishment. The parties agreed that the Builder
should work on a cost-plus contract because of the premises seemed to be in a
flood zone area.
After executing the contract, the builder engaged
an engineer to determine the stability of the ground. Unfortunately, the
engineer’s recommendation was that significant piers would need to installed.
The parties agree it would be more cost effective and result in a better build
if the house was knocked down and rebuilt.
This is where the Cost of Project Commencement
Delay comes into play. The compliance documents approved by Council were now
inconsistent with the new work to be performed. The Builder was expecting to
commence the work in May, it is now September.
On reliance on this important long term client’s
work commencing and the significant work required for this custom project, the
builder cleared out his schedule and refused work from April onward. The
builder accepted a few small odd jobs to keep him going but nothing really
substantial. It took the Builder until August to approach me and describe the
problems he is experiencing from the delay with this project commencing. I have
collated his problems described below.
Trevor the
Lump Sum Builder - $1M+ Contract
The Client consisted of owner-occupiers of a
block of units in Bondi. The Client engaged an architect to prepare all
drawings and specifications and more importantly to project manage the job. The
Client engaged a building and construction lawyer to negotiate the contract
terms and conditions.
The project is in a high profile location - Bondi
Beach. The Client(s) are prominent long term residence of the community. The
project is the first time build for the builder – a knock down re-build of
apartment block. The builder viewed the project as a significant opportunity to
demonstrate his building skills with a view to extending his business into
apartment style building as well as his current portfolio of residential
refurbishments and builds. Most importantly, the value of the contract was in
the millions of dollars so the builder wanted to ensure he devoted his
attention to it.
The Builder, as you would expect, blocked out his
sales and construction pipeline.
Everything seemed to be on track from negotiating
the contract up to the time of contract execution. Then out of left field one
of the unit owners notified everyone that their finance has not yet been approved.
The project has been delayed for more than 4 months now.
John the
Commercial Contractor - $1M+ Contract
This commercial contractor specialises in
high-end commercial windows and doors. The project was in a prominent CBD
location surrounded by Global award winning buildings. The project was to
design and construct curtain wall around the rooftop of a heritage listed
building as-well-as an extrinsic curtain wall for the linkway adjoining the
heritage building and the new building. Put simply, there weren’t many
contractors who could deliver on this project.
Given the significant risks with the project, the
contractor cleared his sales and project pipeline so that he good focus his
specialised design and engineering skills on this project. In close collaboration
with tier-1 engineers, the builders architect and other specialist contractors,
the contractor worked on the design of the works to draft a building to
stand-out from the rest.
You may have guessed that the builder was delayed
with having the contractor commence his work. The reasons for the delay left
people associated with the project wondering whether the project was cursed.
First, the suppliers for the materials were few and far between given the
specialist quality of the material required. The builder, despite many
engineering reports, encountered numerous latent conditions during prior trade
construction particularly when coming out of the ground. Then the Gods got angry and the project
experienced some of the worst rainy weather in many many years.
Unfortunately for the contractor, his work
requires significant capital investment into materials. Being the diligent
contractor that he is, he purchased all the material he required, fabricated
this material, and had everything to go ready, as demanded by his dictating
commercial builder under the construction contract and construction program.
The project was delayed by 5 months.
Summary of
Reasons for Project Commencement Delay
1.
Change in scope of work
2. Incomplete or incorrect scope of work
3. External service provider design and drawings
4. Council approval
5. Lack of or change to financial circumstance of client
6. Weather
7.
Latent condition identified in
prior sequence of work
The Costs
of the Project Delay in Commencing
1.
No revenue generated from the expected
project – the flow on effects of that are obviously significant.
2. Dead sales pipeline – he blocked out the construction period because
it was a cost-plus project and now this construction period is being extended
every day by the delay with the construction commencement.
3. Increased cost with materials. Right now, Sydney is experiencing
significant boom in construction and it feels like suppliers are increasing
their prices by the day.
4. Significant capital being invested and money being locked up
5. Overhead costs being incurred without any work – full-time wages,
insurances, rent etc
6.
Idle time for workers and
company-wide – leading to decreased morale and wasted skill-set
Pondering on these scenarios, I can’t help but
wonder how many projects are delayed and the flow on affects of these delays.
These delays were not expected by either of these builders or the commercial
contractor but I know that the cost of the project commencement delay has left the
small business out of pocket and hurt their successful businesses. I will blog
about at a later date what are some things a commercial contractor can do to
manage the risk of project delay and managing the associated costs with these.
John Dela Cruz
Small Builders – Building Software
Founder and CEO
About the Author
John Dela Cruz is a specialist
building and construction lawyer who works with small builders and commercial
contractors. John is passionate about helping small builders and commercial
contractors build sustainable businesses. As well as being a lawyer, John is
the Founder and CEO of Small Builders, Building Software. John holds numerous
qualifications and memberships including being a member of the Master Builders
Association of NSW.
No comments:
Post a Comment